Formula
Worked example: T = 480, D = 240 → 2
Study notes
- Takt is German for a precise interval of time, such as a musical meter.
- First used as a production management tool in the German aircraft industry in the 1930s, as the interval at which aircraft were moved to the next production station.
- Widely utilized within Toyota in the 1950s and in widespread use throughout the Toyota supply base by the late 1960s.
- Toyota typically reviews the takt for a process every month, with a tweaking review every 10 days.
- The stated purpose is to precisely match production with demand.
- A second worked case in the source: demand of two new products per month gives a takt time of two weeks.