Every Product Every Interval (EPEI)

EPEI (written EPEx in the text) is the frequency with which the different part numbers assigned to a machine or process are produced. If every part number assigned to a machine is produced once every three days, then EPEx is three days. A small EPEx lets each part number be made in small lots, which minimises inventories in the system.

Source checked1/1 values · 2026-10-25Metric

Specification

1 source
Kindmetric

Study notes

  • EPEx is stated to be the frequency with which different part numbers are produced in a production process or system.
  • Example given: if a machine is changed over in a sequence so that every part number assigned to it is produced every three days, EPEx is three days.
  • In general it is good for EPEx to be as small as possible, so that small lots of each part number are produced and inventories in the system are minimised.
  • A machine's EPEx depends on its changeover times and on the number of part numbers assigned to it.
  • A machine with long changeovers (and large minimum batch sizes) running many part numbers will inevitably have a large EPEx unless changeover times or the number of part numbers can be reduced.
  • The document cross-references Heijunka; no entry for Heijunka is available in the reference list.